Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
The Admin and Science Additions continue to progress, with exterior enclosure, interior framing, and site concrete work advancing. Renovations within the existing building are also moving forward, including ceiling and interior finish work.
At the Admin Addition, structural steel and roof decking are complete, with exterior sheathing now underway. At the Science Addition, grade-beam waterproofing and underground utility rerouting are nearing completion.
Renovations to 10 classrooms and two science labs are complete and in use for Phases 1 – 4. Steel erection for the Admin Addition continues. Â Concrete grade beams for the Science Addition have been poured and the forms have been stripped.
The Admin Addition has begun vertical construction with structural steel erection in progress. Interior renovations continue advancing with drywall installation & painting. Flooring and ceiling installation will quickly follow.
Phase 3 interior renovations of the existing campus are rapidly advancing as demolition nears completion and framing activities are underway.
The concrete slab at the new Administration Addition has been poured. Structural steel erection will soon follow. The Science Addition’s site has been prepared for upcoming concrete slab pour. Internal renovations continue with drywall hanging, painting and ceiling grid installation.
Foundation work for the new Administration Addition continues to advance, with piers, grade beams, and underground MEP now complete. Site preparation for the Science Addition remains ongoing. In the existing building, Phase 1 renovations have progressed to drywall installation and finishing.
Foundation work is advancing on the new Administration and Science Additions, with site preparations and structural work underway. Renovations in the existing building have begun, with interior improvements now in progress.Â
Piers have been drilled and poured, with grade beam excavation underway at the Administration Addition site. The Science Addition site subgrade excavation is in currently in progress.
The Additions are underway, with pad excavations currently in progress. Phase 1 renovation areas have been prepped and are ready to begin. Retaining wall construction is in progress, with excavation activities initiated & site work advancing.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.