Meadowbrook Middle School

This Project is Under Construction.

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
2001 Ederville Road, Fort Worth, TX 76103, USA
Budget
$48,454,422
New Construction
21,579 SF
Renovations
84,869 SF
Construction Start
November 03, 2025
Anticipated Opening
Continued Use
Construction End
Q1 2028

Project Team

Cameron Whitaker
Owner’s Representative
Pete Valdez
Deputy Program Director
Contractor
Northridge Construction Group
pfluger logo.
Architect
Pfluger Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
10/21/2026
Meadowbrook Middle School:
Momentum Across Campus

The Admin and Science Additions continue to progress, with exterior enclosure, interior framing, and site concrete work advancing. Renovations within the existing building are also moving forward, including ceiling and interior finish work.

09/25/2026
Meadowbrook Middle School:
Additions Update

At the Admin Addition, structural steel and roof decking are complete, with exterior sheathing now underway. At the Science Addition, grade-beam waterproofing and underground utility rerouting are nearing completion.

08/27/2026
Meadowbrook Middle School:
Classroom Renovations

Renovations to 10 classrooms and two science labs are complete and in use for Phases 1 – 4. Steel erection for the Admin Addition continues.  Concrete grade beams for the Science Addition have been poured and the forms have been stripped.

07/28/2026
Meadowbrook Middle School:
Vertical Construction at the Admin Addition

The Admin Addition has begun vertical construction with structural steel erection in progress. Interior renovations continue advancing with drywall installation & painting. Flooring and ceiling installation will quickly follow.

06/22/2026
Meadowbrook Middle School:
Phase 3

Phase 3 interior renovations of the existing campus are rapidly advancing as demolition nears completion and framing activities are underway.

05/21/2026
Meadowbrook Middle School:
Admin Addition’s Concrete Slab

The concrete slab at the new Administration Addition has been poured. Structural steel erection will soon follow. The Science Addition’s site has been prepared for upcoming concrete slab pour. Internal renovations continue with drywall hanging, painting and ceiling grid installation.

04/23/2026
Meadowbrook Middle School:
Maintaining Momentum

Foundation work for the new Administration Addition continues to advance, with piers, grade beams, and underground MEP now complete. Site preparation for the Science Addition remains ongoing. In the existing building, Phase 1 renovations have progressed to drywall installation and finishing.

03/25/2026
Meadowbrook Middle School:
Foundation Progress

Foundation work is advancing on the new Administration and Science Additions, with site preparations and structural work underway. Renovations in the existing building have begun, with interior improvements now in progress. 

02/25/2026
Meadowbrook Middle School:
Building Addition Foundation

Piers have been drilled and poured, with grade beam excavation underway at the Administration Addition site.  The Science Addition site subgrade excavation is in currently in progress.

01/27/2026
Meadowbrook Middle School:
New Building Additions & Phase 1

The Additions are underway, with pad excavations currently in progress. Phase 1 renovation areas have been prepped and are ready to begin. Retaining wall construction is in progress, with excavation activities initiated & site work advancing.