Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
Exterior brickwork is nearing completion, while the Gym/Storm Shelter’s interior wall installation continues making progress. Ceiling grid installation and base coat paint application is underway in classroom areas.
Drywall installation is nearing completion as crews finalize the kitchen build out. Exterior glazing and masonry work continue to progress across the campus.
Roof work and window installation continue at the Campus Addition with masonry installation to follow. Interior wall framing is complete while MEP rough-ins are in progress.
Phase 1, the Campus Addition, continues with exterior sheathing and roof installation. Building enclosure activities are underway as well. This includes installation of the air/water barrier, window systems, and exterior cladding.
The Campus Addition’s structural steel has been erected, promptly followed by the metal roof deck installation. Sheathing installation is also in progress in preparation for exterior finishing.
Structural precast panels forming the campus storm shelter were hoisted, erected and installed at the Gym Addition.
Site work continues, hollow core planks are set while underslab mechanical, electrical and plumbing work advances at the additions.
The project continues to make progress on the Addition’s foundation elements. Grade beams have been successfully poured at the Cafeteria/Gym wing and the Admin/Media site. Work is actively underway on the Kinder/PreK wing grade beams, with completion scheduled by the end of the month. Backfilling operations is scheduled to support site stabilization.Â
Piers have been poured for the new classroom addition and grade beams in the new kitchen area are in place. Coordination with the electric utility is moving forward and under slab plumbing will be starting soon in preparation for the concrete slab pour.
The new storm drainage line installation is compete and work has begun on the piers for the new building and site grading operations. Next steps are forming and setting the grade beams to connect and support the piers as part of the foundation system.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.