Elementary School #1 Replacement & Consolidation at Eastern Hills Site

This Project is Under Construction

Key Information

Scope of Work:
This project provides a newly constructed facility.
 
Program Initiatives Addressed:

  • Elementary School Facility
  • Campus Replacement
Design Process
Construction Process
2112 Canton Dr, Fort Worth, TX 76112, USA
Budget
$67,238,659
New Construction
92,870 SF
Renovations
N/A
Construction Start
February 27, 2026
Anticipated Opening
August 2027
Anticipated Construction End
Q4 2027

Project Team

Stoney Crump
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Sedalco | Post L JV
BRW Architects logo.
Architect
BRW

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
06/17/2026
Eastern Hills Elementary School:
Site Utilities and Infrastructure

The detention tank and storm water system installation is in progress. The storm shelter formwork continues.

05/29/2026
Eastern Hills Elementary School:
Storm Shelter Formwork

Below-grade storm shelter wall forming and steel reinforcing is underway in preparation for concrete pouring.

04/29/2026
Eastern Hills Elementary School:
Pier Drilling

Pier drilling is underway, creating a strong vertical foundation element to suppot the new structure and will advance to grade beam work next.

03/26/2026
Eastern Hills Elementary School:
Under Construction

FWISD, PROCEDEO, and awarded General Contractor, Sedalco|Post L (JV), broke ground marking the beginning of this project; the Eastern Hills High School Highlander Band helped set the tone of this memorable occasion.  Without delay, the crew began site preparation in advance of foundation work.