Elementary School #1 Replacement & Consolidation at Eastern Hills Site

This Project is Under Construction

Key Information

Scope of Work:
This project provides a newly constructed facility.
 
Program Initiatives Addressed:

  • Elementary School Facility
  • Campus Replacement
Design Process
Construction Process
2112 Canton Dr, Fort Worth, TX 76112, USA
Budget
$67,238,659
New Construction
92,870 SF
Renovations
N/A
Construction Start
February 27, 2026
Anticipated Opening
August 2027
Anticipated Construction End
Q4 2027

Project Team

Stoney Crump
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Sedalco | Post L JV
BRW Architects logo.
Architect
BRW

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/30/2026
Eastern Hills Elementary School:
Summer Strides

The dual purpose Gym/Storm Shelter’s wall forming continues to advance. Concrete has been poured for the spread footings and structural steel is staged for next steps. The southwest driveway is graded and prepped for the upcoming concrete pour.

06/17/2026
Eastern Hills Elementary School:
Site Utilities and Infrastructure

The detention tank and storm water system installation is in progress. The storm shelter formwork continues.

05/29/2026
Eastern Hills Elementary School:
Central Wing Wall Forming

Below-grade wall forming and steel reinforcing are underway ahead of the upcoming concrete pour at the future Administration Office site.

04/29/2026
Eastern Hills Elementary School:
Pier Drilling

Pier drilling is underway, creating a strong vertical foundation element to suppot the new structure and will advance to grade beam work next.

03/26/2026
Eastern Hills Elementary School:
Under Construction

FWISD, PROCEDEO, and awarded General Contractor, Sedalco|Post L (JV), broke ground marking the beginning of this project; the Eastern Hills High School Highlander Band helped set the tone of this memorable occasion.  Without delay, the crew began site preparation in advance of foundation work.