Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
Phase 1, the Campus Addition, continues with exterior sheathing and roof installation. Building enclosure activities are underway as well. This includes installation of the air/water barrier, window systems, and exterior cladding.
The Campus Addition’s structural steel has been erected, promptly followed by the metal roof deck installation. Sheathing installation is also in progress in preparation for exterior finishing.
Structural precast panels forming the campus storm shelter were hoisted, erected and installed at the Gym Addition.
Site work continues, hollow core planks are set while underslab mechanical, electrical and plumbing work advances at the additions.
The project continues to make progress on the Addition’s foundation elements. Grade beams have been successfully poured at the Cafeteria/Gym wing and the Admin/Media site. Work is actively underway on the Kinder/PreK wing grade beams, with completion scheduled by the end of the month. Backfilling operations is scheduled to support site stabilization.Â
Piers have been poured for the new classroom addition and grade beams in the new kitchen area are in place. Coordination with the electric utility is moving forward and under slab plumbing will be starting soon in preparation for the concrete slab pour.
The new storm drainage line installation is compete and work has begun on the piers for the new building and site grading operations. Next steps are forming and setting the grade beams to connect and support the piers as part of the foundation system.
Maudrie Walton Elementary is now under construction and Sedalco Construction Services has begun by demolishing the existing portables and dirt work cuts & fills. Storm drains are being installed in the new classroom addition area, layout and pier drilling to follow.
FWISD, PROCEDEO, and awarded General Contractor, Sedalco Construction, broke ground marking the beginning of this project which includes a major building addition, new classrooms, a media center, fine arts rooms, a storm shelter, and a playground.
The new Maudrie Walton Elementary School is on schedule to begin construction during Q1 of 2025. The project will include the construction of new classrooms, science & collaboration areas, a new media center & performance arts area, new cafeteria & kitchen, and new administration spaces. Pictured are conceptual renderings of the new front entry.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.
