Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
The Orchestra/Science Addition’s concrete floor slab has been poured. Phase 1 renovations have progressed to interior finishing with ceiling framing and grid installation, HVAC and electrical rough-ins, painting, and wall tile installation.
The Orchestra/Science Additon slab has been poured and shoring is in progress. MEP rough-ins, and drywall installation continue making progress at the Reception and Admin offices.
Concrete grade beams have been poured and the forms stripped at the Orchestra/Science Addition. Wall framing at the Admin renovations is complete. Rough-ins and drywall installation are in progress.
The Science/Orchestra Addition foundation work is advancing rapidly with grade beam forming at the site. Interior renovations are in progress with framing, drywall and ceiling tile installation underway at the Admin offices and Theater Room.
The north corridor’s floor tile abatement marks the beginning of summer interior renovations. Outdoors, site surfacing is complete to stage the construction trailer and laydown. Earthwork for the new addition is making progress.
Applied Learning Academy is now under construction. Tienert Construction has begun implementing site preparation plans including the installation of construction barricade fencing and tree protection fencing.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.