Forest Oak Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • Life cycle improvements – Mechanical, electrical, plumbing, technology, security, finishes, roofing.
  • New secured front entry vestibule.
  • Minor interior renovations – corridors, commons, media center, and cafeteria.
Design Process
Construction Process
Fort Worth Independent Sch Dst, 3221 Pecos Street, Fort Worth, TX 76119, USA
Budget
$64,135,847
New Construction
73,059 SF
Renovations
91,573 SF
Construction Starts
January 22, 2025
Anticipated Opening
Q3 2027
Trustee
Wallace Bridges

Project Team

Cameron Whitaker
Owner’s Representative
Headshot of Drew Schott.
Drew Schott
Construction Manager
Contractor
SEDALCO / Post L
Perkins and Will logo.
Architect
Perkins&Will

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/29/2025
Forest Oak Middle School: Construction Progresses Across Campus

Phase 1 classrooms are advancing with lighting ceiling grid, and corridor tile work is completed. Site improvements continue, including bus lane and entry paving. Foundation work for the building addition is underway.

06/26/2025
Forest Oak Middle School: Interior Renovations and Site Prep in Progress

Demolition continues across classrooms and the east wing. Site work includes pad prep for the new addition. IPRC work and library abatement are also underway, with multiple scopes active this month.

05/27/2025
Forest Oak Middle School: Site Work Progressing Ahead of New Addition

Demolition of the east parking lot is complete, and preparations are underway for underground utility work to support the new building addition. Safety preparations are underway at the exterior locker room, with demolition scheduled to begin in June.

03/31/2025
Forest Oak Middle School: Spring Update

We have completed the pour of concrete in the southern parking lot. There are a total 74 parking spaces for staff. With this complete, we are now preparing to start construction in the three-story addition.

11/22/2024
Forest Oak MS: Construction Progress

Construction for the Forest Oak Middle School project began in Q4 2024, and started with the completion of a portable village built by contractor FH Paschen. 14 portable units are being relocated onto Forest Oak’s Middle School Campus to house 6th Graders that are relocating from Glencrest campus. The portable scope includes utilities, MEP, and security & safety.

 

 

09/03/2024
Forest Oak MS: Exterior Conceptual Renderings

The Procedeo team is nearly complete with construction procurement for the Forest Oak Middle School project. Pictured are exterior conceptual renderings; reflecting an aerial view of the renovated campus and proposed addition building. Construction is anticipated to begin during Q1 of 2025.

04/30/2023
Forest Oak MS: Interior Conceptual Renderings

Interior conceptual renderings of Forest Oak Middle School; Reflecting student collaboration areas in the renovated campus!!!