Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Work continues on the new front entrance and 2-story courtyard additions, with glass installation and interior buildout in progress. Renovation efforts in the kitchen and cafeteria areas are ramping up.
The front and courtyard additions remain on track for completion in July 2025. The northwest front addition is beginning in late May, with completion scheduled for the fall 2025. Interior renovations are also starting this month.
Progress continues at Jacquet MS, with glass installed on the second floor and exterior façade work now underway. The front and courtyard additions remain on track for completion of July 2025.
Con-Real contractors continue to work on the courtyard and new addition. Anticipated completion for the courtyard and new front addition is July 2025.
The new front addition and courtyard addition are in progress at J. Martin Jacquet Middle School. Con-Real contractors are focused on mechanical, electrical, and plumbing. The pre-cast walls for the the courtyard addition are scheduled to be completed the first week of February 2025.
Demolition in areas like the cafeteria windows and girls locker room storage area are also ongoing.
Demolition and site preparation at J. Martin Jacquet Middle School is now complete. Pier drilling and excavation at the new addition areas is also complete and all utilities in the two new addition areas have been relocated!
Con-Real is now focused on installing the foundation’s perimeter.
Con-Real began construction on the J. Martin Jacquet Middle School campus on June 26, 2024. The new two-story addition building will also feature a courtyard and a new, secure front entry vestibule. Demolition and site preparation is on going as we near the end of August 2024.
We are here! An NTP to begin construction on J. Martin Jacquet Middle School was granted on June 26, 2024. The team is taking the necessary steps to prepare for building renovations and site demolition to make space for the new Addition building.
As Jacquet Middle School makes progress through the design phases of the 2021 Bond Program, new renderings are in development- capturing common areas, collaboration spaces, and conceptual classrooms.
Exterior conceptual rendering of J. Martin Jacquet Middle School; Reflecting a renovated front entry to the school.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.