J. Martin Jacquet Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
 
Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
2501 Stalcup Rd, Fort Worth, TX 76119, USA
Budget
$44,046,438
New Construction
31,975 SF
Renovations
103,524 SF
Construction Start
June 26, 2024
Anticipated Opening
Continued Use
Anticipated Construction End
Q4 2026

Project Team

Stoney Crump
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Con-Real, LLC
BLDD Architects logo.
Architect
BLDD Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/29/2026
J. Martin Jacquet Middle School:
Summer Highlights

Phase 4 Science Lab renovations are nearing completion, ahead of the first day of school. The new fire lane, driveway, and parking area has been poured and surface finishing is underway.

06/16/2026
J. Martin Jacquet Middle School:
Science Labs Update

Phase 4 renovations in the Science Wing are rapidly advancing. Outdoor portable classrooms have been demolished and cleared out, making way for a new fire lane, driveway, and parking spaces.

05/28/2026
J. Martin Jacquet Middle School:
Phase 4 – Science Wing

Science lab renovations have begun, move out and demolition activities are underway. Renovations have been completed in previous Phase 4 areas. New furniture installation is scheduled during summer. Exterior site improvements including the removal of portables and the south driveway reconstruction have begun.

04/30/2026
J. Martin Jacquet Middle School:
Phase 4 Advancing

Paritioned into sections, Phase 4 is maintaining momentum; renovations on the 2nd floor classrooms, offices and staff lounge are in their final stages and prepping for turnover. Meanwhile, in the 1st floor admin offices and classrooms, MEP trades are in full swing with overhead rough-ins.

03/26/2026
J. Martin Jacquet Middle School:
Furniture & Phase 4

New furniture, fixtures and equipment for the Performing Arts Addition and the Phase 3 classrooms were installed during Spring Break.  Crews worked to assemble, install and move furniture into place.  The project’s final phase, renovating the school’s internal group of classrooms and offices is underway, currently working on MEP and framing.

02/24/2026
J. Martin Jacquet Middle School:
Performing Arts Addition Finishing Touches

The Performing Arts building addition is complete and final interior details and finishes are underway.

01/27/2026
J. Martin Jacquet Middle School:
Addition & Renovations Update

Phase 2 Performing Arts addition is nearing completion. Phase 3 renovations, Auditorium, and locker room renovations are complete and ready for occupancy. Phase 4 renovations beginning soon.

12/17/2025
J. Martin Jacquet Middle School:
Phase 2 & 3 Progress

Phase 2 auditorium, locker room, and gym life safety upgrades are progressing. Phase 3 interior renovations and the Performing Arts addition remain on track for early next year turnover.

11/26/2025
J. Martin Jacquet Middle School:
Phase 2A Renovations Complete

Phase 2A interior renovations are now complete, with upgraded spaces preparing for turnover following the Thanksgiving break. Work on the auditorium is also nearing completion. The Performing Arts addition continues to advance towards its final stages. Phase 3 classroom renovations are ongoing.

10/31/2025
J. Martin Jacquet Middle School:
Phase 2B & 2C Renovations Complete & In Use

Phase 2B and 2C renovations, including the cafeteria, kitchen, media center, classrooms & collaboration rooms have been turned over to the district and are in-use.  Locker rooms improvements are on track for completion in November 2025.  Phase 2A renovations & new addition, Performing Arts areas are scheduled for December 2025 completion.