J. Martin Jacquet Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New building additions.
  • New fire lane and landscape areas.
  • Removal of portables.
  • Secured front entry vestibule.
  • Major interior renovations, including. commons/cafeteria and corridors.
Design Process
Construction Process
2501 Stalcup Road, Fort Worth, TX 76119, USA
Budget
$44,046,438
New Construction
31,975 SF
Renovations
109,557 SF
Construction Starts
June 26, 2024
Anticipated Opening
Q3 2026
Trustee
Quinton Phillips

Project Team

Stoney Crump
Owner’s Representative
Headshot of Edsel Gaitonde.
Edsel Gaitonde
Construction Manager
Contractor
Con-Real, LLC
BLDD Architects logo.
Architect
BLDD Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
06/26/2025
J. Martin Jacquet Middle School: Additions and Renovations Advanc

Work continues on the new front entrance and 2-story courtyard additions, with glass installation and interior buildout in progress. Renovation efforts in the kitchen and cafeteria areas are ramping up.

05/27/2025
J. Martin Jacquet Middle School: Additions Progress and Interior Renovations Begin

The front and courtyard additions remain on track for completion in July 2025. The northwest front addition is beginning in late May, with completion scheduled for the fall 2025. Interior renovations are also starting this month.

04/29/2025
J. Martin Jacquet Middle School: Front and Courtyard Additions Progressing

Progress continues at Jacquet MS, with glass installed on the second floor and exterior façade work now underway. The front and courtyard additions remain on track for completion of July 2025.

03/31/2025
J. Martin Jacquet Middle School: Spring Update

Con-Real contractors continue to work on the courtyard and new addition. Anticipated completion for the courtyard and new front addition is July 2025.

01/23/2025
J. Martin Jacquet Middle School: January 2025 Update

The new front addition and courtyard addition are in progress at J. Martin Jacquet Middle School. Con-Real contractors are focused on mechanical, electrical, and plumbing. The pre-cast walls for the the courtyard addition are scheduled to be completed the first week of February 2025.

Demolition in areas like the cafeteria windows and girls locker room storage area are also ongoing.

11/21/2024
J. Martin Jacquet Middle School: Site Preparation is Complete!

Demolition and site preparation at J. Martin Jacquet Middle School is now complete. Pier drilling and excavation at the new addition areas is also complete and all utilities in the two new addition areas have been relocated!

Con-Real is now focused on installing the foundation’s perimeter.

08/22/2024
J. Martin Jacquet Middle School: Preparation for the New Building is Underway

Con-Real began construction on the J. Martin Jacquet Middle School campus on June 26, 2024. The new two-story addition building will also feature a courtyard and a new, secure front entry vestibule. Demolition and site preparation is on going as we near the end of August 2024.

07/22/2024
J. Martin Jacquet Middle School is Under Construction!

We are here! An NTP to begin construction on J. Martin Jacquet Middle School was granted on June 26, 2024. The team is taking the necessary steps to prepare for building renovations and site demolition to make space for the new Addition building.

02/23/2024
J. Martin Jacquet MS: Conceptual Renderings

As Jacquet Middle School makes progress through the design phases of the 2021 Bond Program, new renderings are in development- capturing common areas, collaboration spaces, and conceptual classrooms.

10/18/2023
J. Martin Jacquet MS: Exterior Conceptual Renderings

Exterior conceptual rendering of J. Martin Jacquet Middle School; Reflecting a renovated front entry to the school.