Leonard Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
 
Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
8900 Chapin Road, Fort Worth, TX 76116, USA
Budget
$47,247,089
New Construction
29,067 SF
Renovations
118,653 SF
Construction Start
September 3, 2024
Anticipated Opening
August 2026
Anticipated Construction End
Q1 2027

Project Team

Christian Boyd
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Satterfield & Pontikes | F&P Construction (JV)
VLK Architects logo.
Architect
VLK Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
05/21/2026
Leonard Middle School:
Interior Flatwork Continues

Phase 2 interior flatwork continues with the re-pouring and correcting of floor elevation. Additional existing campus renovations have advanced rapidly. Phase 2 demolition and abatement are complete and ductwork and overhead rough-ins are underway.

04/27/2026
Leonard Middle School:
Campus Accessibility

As the campus expanded over time, several outdoor paved areas became interior spaces. As part of the school’s current renovations, sloping and unlevel sections are being rebuilt to create a safer, more accessible campus.

03/25/2026
Leonard Middle School:
Phase 1 Complete & Phase 2 Begins

The newly constructed Science Labs, CTE, Fine Arts, Admin and Main Entrance additions are complete and turned over for use.  Phase 2, renovation of the existing structures begins with demolition.

02/25/2026
Leonard Middle School:
Exterior Concrete Work

Exterior site work is progressing. Concrete is being placed and finished to prepare the driveways, parking lot entrances, sidewalk connections, drop-offs & fire lanes for use.

01/27/2026
Leonard Middle School:
Phase 1 & Addition Update

Flooring and trim out in Phase 1 is wrapping up with ceilings and final paint following closely. Corridor walls are nearing completion in the Fine Arts and Admin additions. Fire lane subgrade is complete and ready for paving.

12/30/2025
Leonard Middle School:
Phase 1 & Area D

Phase 1 finishes are underway with tile and paint progressing in all areas. Exterior panel work is ongoing at the Area D admin addition. Grading and site prep for fire lane is complete.

11/26/2025
Leonard Middle School:
Exterior and Interior Finishes Advancing

Exterior improvements are progressing on the new administration entry, with additional finish work underway inside the Fine Arts and Administration additions. Roofing work is wrapping up as the project continues toward upcoming milestones.

10/31/2025
Leonard Middle School:
Fine Arts & Administration Overhead Work

Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing.  On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete

09/30/2025
Leonard Middle School:
Continued Progress

MEP trades activities continue in the addition and renovation areas. Masonry has been completed in the Fine Arts addition.

08/22/2025
Leonard Middle School:
Progress Across Building and Fine Arts Area

Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.