Leonard Middle School

This Project is Under Construction.

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New building additions of classroom/admin, fine arts, weight room with lobby, and vestibule.
  • Major interior renovations which include media center, girl’s locker room, classroom/science lab, and admin area.
  • Light renovations to sprinkler and fire alarm systems.
Design Process
Construction Process
8900 Chapin Road, Fort Worth, TX 76116, USA
Budget
$50,247,089
New Construction
29,067 SF
Renovations
118,653 SF
Trustee
Dr. Michael Ryan
Construction Starts
September 3, 2024
Anticipated Opening
August 2026
Anticipated Construction End
Q1 2027

Project Team

Headshot of Garret North.
Garrett North
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
SFP2, A Joint Venture, LLC
VLK Architects logo.
Architect
VLK Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
01/27/2026
Leonard Middle School: Phase 1 & Addition Update

Flooring and trim out in Phase 1 is wrapping up with ceilings and final paint following closely. Corridor walls are nearing completion in the Fine Arts and Admin additions. Fire lane subgrade is complete and ready for paving.

12/30/2025
Leonard Middle School: Phase 1 & Area D

Phase 1 finishes are underway with tile and paint progressing in all areas. Exterior panel work is ongoing at the Area D admin addition. Grading and site prep for fire lane is complete.

11/26/2025
Leonard Middle School: Exterior and Interior Finishes Advancing

Exterior improvements are progressing on the new administration entry, with additional finish work underway inside the Fine Arts and Administration additions. Roofing work is wrapping up as the project continues toward upcoming milestones.

10/31/2025
Leonard Middle School: Fine Arts & Administration Overhead Work

Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing.  On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete

09/30/2025
Leonard Middle School: Progress Across Building and Fine Arts Area

Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.

08/22/2025
Leonard Middle School: Progress Across Building and Fine Arts Area

Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.

07/29/2025
Leonard Middle School: Renovation and Additional Work Continues

Roofing continues in the new addition and the renovation area. Underground utilities and the fire lane work scheduled for this summer are complete and concrete is being placed in these areas. The cafeteria received new flooring and wall tile as part of the summer renovation.

06/26/2025
Leonard Middle School: Roofing, Utilities, and Interior Work Continue

Roofing and utility work remain active throughout the site. Crews continue with fiber pathways, roof installation, and buildout of the Fine Arts addition. Progress remains steady in preparation for major summer milestones.

05/27/2025
Leonard Middle School: Exterior and Roofing Work Progressing

Exterior masonry work is complete at the Fine Arts addition, and work has begun on installing structural steel. Roofing is underway at the new administrative wing, while metal wall panel and roof replacement in renovation area are on track for completion this summer.

04/29/2025
Leonard Middle School: Structural and Fine Arts Work Advancing at Leonard

Leonard Middle School is seeing steady progress as structural work wraps up on the new addition. Crews are advancing on the Fine Arts area, completing underground plumbing, and preparing for roof panel installation in May.