Leonard Middle School

This Project is Under Construction.

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New building additions of classroom/admin, fine arts, weight room with lobby, and vestibule.
  • Major interior renovations which include media center, girl’s locker room, classroom/science lab, and admin area.
  • Light renovations to sprinkler and fire alarm systems.
Design Process
Construction Process
8900 Chapin Road, Fort Worth, TX 76116, USA
Budget
$50,247,089
New Construction
29,067 SF
Renovations
118,653 SF
Trustee
Dr. Michael Ryan
Construction Starts
September 3, 2024
Anticipated Opening
August 2026
Anticipated Construction End
Q3 2026

Project Team

Headshot of Garret North.
Garrett North
Owner’s Representative
Headshot of Drew Schott.
Drew Schott
Construction Manager
Contractor
SFP2, A Joint Venture, LLC
VLK Architects logo.
Architect
VLK Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
10/31/2025
Leonard Middle School: Fine Arts & Administration Overhead Work

Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing.  On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete

09/30/2025
Leonard Middle School: Progress Across Building and Fine Arts Area

Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.

08/22/2025
Leonard Middle School: Progress Across Building and Fine Arts Area

Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.

07/29/2025
Leonard Middle School: Renovation and Additional Work Continues

Roofing continues in the new addition and the renovation area. Underground utilities and the fire lane work scheduled for this summer are complete and concrete is being placed in these areas. The cafeteria received new flooring and wall tile as part of the summer renovation.

06/26/2025
Leonard Middle School: Roofing, Utilities, and Interior Work Continue

Roofing and utility work remain active throughout the site. Crews continue with fiber pathways, roof installation, and buildout of the Fine Arts addition. Progress remains steady in preparation for major summer milestones.

05/27/2025
Leonard Middle School: Exterior and Roofing Work Progressing

Exterior masonry work is complete at the Fine Arts addition, and work has begun on installing structural steel. Roofing is underway at the new administrative wing, while metal wall panel and roof replacement in renovation area are on track for completion this summer.

04/29/2025
Leonard Middle School: Structural and Fine Arts Work Advancing at Leonard

Leonard Middle School is seeing steady progress as structural work wraps up on the new addition. Crews are advancing on the Fine Arts area, completing underground plumbing, and preparing for roof panel installation in May.

03/31/2025
Leonard Middle School: Spring Update

All foundation and slab work is complete in addition. Structural steel is underway in the addition. The new roof in the renovation area is anticipated to be completed at the end of April 2025. Existing plumbing is being rerouted in the renovation area.

01/31/2025
Leonard Middle School: Building the Foundation!

Sitework is ongoing at the Leonard Middle School campus. This includes framework foundation and  underground plumbing at the new addition building. The contractor, SPF2, will start the first slab pour during the first week of February 2025.

 

11/21/2024
Leonard Middle School: Phase One of Construction is in Progress!

The contractor, SPF2, for Leonard Middle School is progressing through Phase 1 of construction. Some sitework like pier drilling and excavation is ongoing, but expected to be complete prior to Thanksgiving 2024. Interior progress has also been made; Electrical rough-in and framing for the interior is ongoing through mid-December 2024.