Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing. On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete
Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.
Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.
Roofing continues in the new addition and the renovation area. Underground utilities and the fire lane work scheduled for this summer are complete and concrete is being placed in these areas. The cafeteria received new flooring and wall tile as part of the summer renovation.
Roofing and utility work remain active throughout the site. Crews continue with fiber pathways, roof installation, and buildout of the Fine Arts addition. Progress remains steady in preparation for major summer milestones.
Exterior masonry work is complete at the Fine Arts addition, and work has begun on installing structural steel. Roofing is underway at the new administrative wing, while metal wall panel and roof replacement in renovation area are on track for completion this summer.
Leonard Middle School is seeing steady progress as structural work wraps up on the new addition. Crews are advancing on the Fine Arts area, completing underground plumbing, and preparing for roof panel installation in May.
All foundation and slab work is complete in addition. Structural steel is underway in the addition. The new roof in the renovation area is anticipated to be completed at the end of April 2025. Existing plumbing is being rerouted in the renovation area.
Sitework is ongoing at the Leonard Middle School campus. This includes framework foundation and underground plumbing at the new addition building. The contractor, SPF2, will start the first slab pour during the first week of February 2025.
The contractor, SPF2, for Leonard Middle School is progressing through Phase 1 of construction. Some sitework like pier drilling and excavation is ongoing, but expected to be complete prior to Thanksgiving 2024. Interior progress has also been made;Â Electrical rough-in and framing for the interior is ongoing through mid-December 2024.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.