Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Flooring and trim out in Phase 1 is wrapping up with ceilings and final paint following closely. Corridor walls are nearing completion in the Fine Arts and Admin additions. Fire lane subgrade is complete and ready for paving.
Phase 1 finishes are underway with tile and paint progressing in all areas. Exterior panel work is ongoing at the Area D admin addition. Grading and site prep for fire lane is complete.
Exterior improvements are progressing on the new administration entry, with additional finish work underway inside the Fine Arts and Administration additions. Roofing work is wrapping up as the project continues toward upcoming milestones.
Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing. On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete
Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.
Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.
Roofing continues in the new addition and the renovation area. Underground utilities and the fire lane work scheduled for this summer are complete and concrete is being placed in these areas. The cafeteria received new flooring and wall tile as part of the summer renovation.
Roofing and utility work remain active throughout the site. Crews continue with fiber pathways, roof installation, and buildout of the Fine Arts addition. Progress remains steady in preparation for major summer milestones.
Exterior masonry work is complete at the Fine Arts addition, and work has begun on installing structural steel. Roofing is underway at the new administrative wing, while metal wall panel and roof replacement in renovation area are on track for completion this summer.
Leonard Middle School is seeing steady progress as structural work wraps up on the new addition. Crews are advancing on the Fine Arts area, completing underground plumbing, and preparing for roof panel installation in May.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.