Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
Phase 2 interior flatwork continues with the re-pouring and correcting of floor elevation. Additional existing campus renovations have advanced rapidly. Phase 2 demolition and abatement are complete and ductwork and overhead rough-ins are underway.
As the campus expanded over time, several outdoor paved areas became interior spaces. As part of the school’s current renovations, sloping and unlevel sections are being rebuilt to create a safer, more accessible campus.
The newly constructed Science Labs, CTE, Fine Arts, Admin and Main Entrance additions are complete and turned over for use. Phase 2, renovation of the existing structures begins with demolition.
Exterior site work is progressing. Concrete is being placed and finished to prepare the driveways, parking lot entrances, sidewalk connections, drop-offs & fire lanes for use.
Flooring and trim out in Phase 1 is wrapping up with ceilings and final paint following closely. Corridor walls are nearing completion in the Fine Arts and Admin additions. Fire lane subgrade is complete and ready for paving.
Phase 1 finishes are underway with tile and paint progressing in all areas. Exterior panel work is ongoing at the Area D admin addition. Grading and site prep for fire lane is complete.
Exterior improvements are progressing on the new administration entry, with additional finish work underway inside the Fine Arts and Administration additions. Roofing work is wrapping up as the project continues toward upcoming milestones.
Phase 1, including Fine Arts & Administration additions, roof nearing competition to allow for ceiling install & wall finishing. On the exterior, windows & frames are installed, storefront installation is ongoing, and masonry, insulation, and sheathing are complete
MEP trades activities continue in the addition and renovation areas. Masonry has been completed in the Fine Arts addition.
Electrical and plumbing installations are ongoing in the addition and renovation areas. Roof replacement continues on existing buildings and masonry work is wrapping up in the Fine Arts addition.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.
