Jean McClung Middle School

This Project is Under Construction

Key Information

The Jean McClung Middle School project is under construction. Planned improvements include exterior upgrades, a new secure entry, HVAC replacement, and interior renovations to support specialized programs such as science, CTE, fine arts, PE, and special education.

Design Process
Construction Process
3000 Forest Ave, Fort Worth, TX 76112, USA
Budget
$20,749,082
New Construction
N/A
Renovations
117,282 SF
Construction Start
October 06, 2025
Anticipated Opening
Continued Use
Anticipated Construction End
Q2 2027

Project Team

Christian Boyd
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Satterfield & Pontikes | F&P Construction (JV)
Harrison Konberg architects logo.
Architect
Harrison Kornberg Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
03/25/2026
Jean McClung Middle School: 2nd Level Progress

The 2nd level classroom and science lab wing is progressing in multiple phases, each currently at different stages.  Some rooms have been renovated and turned over for use. Other rooms are preparing for turnover as the remaining rooms begin renovation.  Outdoors, soil stabilization for the chiller pads has begun to support of the upgraded cooling system.

02/25/2026
Jean McClung Middle School: 2nd Level Renovations & Cooling System Upgrade

The initial phase of the 2nd level classroom renovations is complete, and teachers have begun moving back into the finished spaces.  Renovations are now underway in the next section, with the new flooring and wall finishes being installed. Plumbing and site work are in progress to support and upgrade cooling system.

01/27/2026
Jean McClung Middle School: Cafeteria Finishes Complete

Cafeteria and Main Corridor finishes are complete on the 1st level. Additionally, classroom and corridor flooring replacement has begun on the 2nd level and chiller pad prep and piping is underway at the exterior.

12/30/2025
Jean McClung Middle School: Construction Progress

Phase 1B1 and 1B2 are complete. CTE lab is complete, awaiting final inspection for occupancy. Paint and flooring is ongoing in the cafeteria and corridors. Phase 1A1 demo and flooring scheduled for the holiday break.