Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Phase 3 framing and drywall are complete and overhead MEP rough-in activities continue. Phase 4 is underway, with demolition complete and framing and in-wall MEP installation progressing. Foundation work for the addition has advanced, with grade beams poured and slab preparation currently underway.
Phase 3 construction is moving forward with framing, drywall, HVAC, and electrical work underway. The new building addition is also advancing, with foundation work moving forward and and slab placement scheduled next.
Phases 1B and 2B have been completed and turned over to staff and students. Phase 3, featuring demolition, overhead MEP installation, and exterior window removal in preparation for new window installation are in progress. In the addition, pier drilling is nearly complete.
Phase 2B classrooms are close to completion with flooring, inspections, and casework installation underway. Furniture installation is scheduled by late September. The JCC and wight room are progressing, with equipment installation set for end of September. Foundation preparations for the addition are also moving forward.
Phase 1 classrooms were completed and ready for the first day of school. Work continues in Phase 2, with completion expected in September, while roofing and HVAC installations progress across the campus.
Phase 1 spaces are nearing completion with systems and finishes installed. In Phase 2, framing and drywall are underway. On-site utility work continues with power restoration expected by late July.
Drywall installation is in progress in Phase 1 following MEP and framing work. Phase 2 is now in abatement. Civil site upgrades, including the water line and fire line, are complete, supporting continued momentum on interior renovations.
Phase 1 demolition is complete, and overhead mechanical, electrical, and plumbing installations are in progress. Underground electrical work is complete and water installation and fire protection lines for the new addition are underway.
FWISD, PROCEDEO, Candence McShane, and Morales broke ground on major renovations and a new fine arts building that will include performance spaces for Mariachi, orchestra, band, choir and theater.
As of August 2024, Parkhill Architects are working through the Construction Document phase of design for the Riverside Middle School campus. The school’s scope currently consists of major interior renovations, plus a brand new building that will house the fine arts extracurricular programs- including performance areas for Mariachi, orchestra, band, choir, and theater.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.