Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
The band hall is nearing completion; the new fine arts building addition and renovated kitchen will be open in the next couple of weeks. Renovations to the 2nd floor continue and are on schedule for an early spring opening.
The new administration addition and new main entrance opened for students this month. The fine arts addition and new expanded kitchen will open in January. Interior renovations continue to make progress on the 2nd floor. The contractors have also started to replace the old exterior façade.
The new Administration Addition, school entrance, and expanded kitchen have reached their final stages and are expected to wrap up as scheduled. Work is also progressing on the new Performance Arts addition, which remains on track for January completion. Renovation activity continues on the second floor.
The new expanded kitchen is scheduled for completion toward the end of November, while the entrance & administration area continue tracking to be finished mid-November. The Fine Arts addition and second floor classroom renovations are also underway and making great progress.
The new administration area and school entrance are scheduled to be ready in November. On the second floor, demolition is complete, and electrical and HVAC work is underway.
The new media center, 5 classrooms, and renovated cafeteria opened for the start of school. The new administration addition and renovated kitchen will be ready later this fall while work on the Fine Arts addition continues.
Renovated cafeteria, media center, and new classrooms will be ready for the new school year. The two new additions are progressing towards a fall completion. The 2nd Floor classroom demolition has started.
Exterior and interior upgrades continue on track. Crews are wrapping up HVAC installations and window replacements. Ongoing progress inside the new administrative areas.
Structural steel is complete, and both exterior and interior wall framing are underway on the new additions. Interior renovations have also begun. This summer, construction will focus on the kitchen, cafeteria, restroom, and corridor areas.
April brought the successful turnover of 14 classrooms and office spaces at Wedgwood Middle School. Renovation work continues, with active progress on the new entrance and Fine Arts addition.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.