Wedgwood Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • Two new building additions.
  • Renovations to the existing building.
Design Process
Construction Process
3909 Wilkie Way, Fort Worth, TX 76133, USA
Budget
$61,694,266
New Construction
38,436 SF
Renovations
110,787 SF
Trustee
Anne Darr
Construction Starts
July 25, 2024
Anticipated Opening
January 2026
Anticipated Construction End
Q3 2026

Project Team

general contractor icon.
OR TBD
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Cadence McShane | Morales JV
WRA logo.
Architect
WRA Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
01/27/2026
Wedgwood Middle School: Fine Arts/Band Hall

The band hall is nearing completion; the new fine arts building addition and renovated kitchen will be open in the next couple of weeks. Renovations to the 2nd floor continue and are on schedule for an early spring opening.

12/30/2025
Wedgwood Middle School: Interior Renovations Continue

The new administration addition and new main entrance opened for students this month. The fine arts addition and new expanded kitchen will open in January. Interior renovations continue to make progress on the 2nd floor. The contractors have also started to replace the old exterior façade.

11/26/2025
Wedgwood Middle School: Additions Nearing Completion

The new Administration Addition, school entrance, and expanded kitchen have reached their final stages and are expected to wrap up as scheduled. Work is also progressing on the new Performance Arts addition, which remains on track for January completion. Renovation activity continues on the second floor.

10/31/2025
Wedgwood Middle School: New Expanded Kitchen Progress

The new expanded kitchen is scheduled for completion toward the end of November, while the entrance & administration area continue tracking to be finished mid-November. The Fine Arts addition and second floor classroom renovations are also underway and making great progress.

09/30/2025
Wedgwood Middle School: Additions Advancing Toward Completion

The new administration area and school entrance are scheduled to be ready in November. On the second floor, demolition is complete, and electrical and HVAC work is underway.

08/26/2025
Wedgwood Middle School: Campus Improvements Continue

The new media center, 5 classrooms, and renovated cafeteria opened for the start of school. The new administration addition and renovated kitchen will be ready later this fall while work on the Fine Arts addition continues.

07/29/2025
Wedgwood Middle School: Renovations Prepare Campus for Fall

Renovated cafeteria, media center, and new classrooms will be ready for the new school year. The two new additions are progressing towards a fall completion. The 2nd Floor classroom demolition has started.

06/26/2025
Wedgwood Middle School: Interior Renovations and Summer Work Underway

Exterior and interior upgrades continue on track. Crews are wrapping up HVAC installations and window replacements. Ongoing progress inside the new administrative areas.

05/27/2025
Wedgwood Middle School: Framing Progress and Summer Renovations Planned

Structural steel is complete, and both exterior and interior wall framing are underway on the new additions. Interior renovations have also begun. This summer, construction will focus on the kitchen, cafeteria, restroom, and corridor areas.

04/30/2025
Wedgwood Middle School: Classroom Turnovers and Renovations Continue

April brought the successful turnover of 14 classrooms and office spaces at Wedgwood Middle School. Renovation work continues, with active progress on the new entrance and Fine Arts addition.