Scope of Work:
This project includes new additions and existing site renovations.
Key Improvements:
Phase 4 Classrooms are complete and successfully turned over for district use. The Interior Courtyard turf and benches have been installed.
Irrigation has wrapped up around the building & newly installed landscaping and back filled curbs are now visible. Progress continues in Phase 4 classrooms, counselor’s area, nurses station, & teachers work room.
The newly designed classrooms being renovated on the first and second floors are taking shape with walls going up. Additional Phase 4 progress includes under slab plumbing in the new staff lounge and new storefront doors at the old entrance.
Phase 4 renovation work is moving forward with reconstruction underway. The remaining Phase 3 classrooms and the Media Center have been completed and turned over for district use. The new front entrance has also opened, marking another key milestone for the campus.
Marking another milestone, the new entrance is nearing completion. Phase 4 demo is currently underway, paving the way for the next stage of improvements.
Phase 2 administrative areas and classrooms, along with Phase 3 classrooms, have been turned over for district use. Additional storage rooms and the new front entry will open in the coming weeks as Phase 4 renovations move forward.
Renovations in Phases 2 and 3 are on track for September completion. Furniture delivery and set up will follow. The newly opened Phase 2 parking lot now provides ample campus parking.
Phase 2 and 3 renovations will continue through the end of summer. Furniture installation and room setup are scheduled for early August. The second portion of the parking lot is being poured and will be ready for the first day of school.
Phase 2 renovations continue in the administrative area, with the first round of FFE (Furniture, Fixtures, and Equipment) deliveries expected this July. Gym reconstruction and parking lot work are progressing. Phase 3 demo prep and civil work is underway.
Phase 2 renovation remains underway, including ongoing gym reconstruction and work on the Phase 2 parking lot. Preparations for Phase 3 demolition are scheduled to begin this summer.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.