Como Success Academy

This Project is Under Construction

Key Information

Scope of Work:
This project includes new additions and existing site renovations.

 

Key Improvements:

  • New entrance with courtyard canopy & window replacement
  • New parking spaces
  • Renovations to gymnasium, auditorium, cafeteria, corridors & fire sprinkler system
Design Process
Construction Process
5824 Libbey Ave, Fort Worth, TX 76107, USA
Budget
$17,637,150
New Construction
N/A
Renovations
54,293 SF
Trustee
Kevin Lynch
Construction Starts
September 3, 2024
Anticipated Opening
Continued Use
Anticipated Construction End
Q3 2026

Project Team

Headshot of Cale Wilkinson.
Cale Wilkinson
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Teinert Construction
Architect
Kline Hardin

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
02/24/2026
Como Success Academy: Phase 4 Complete

Phase 4 Classrooms are complete and successfully turned over for district use. The Interior Courtyard turf and benches have been installed.

01/27/2026
Como Success Academy: Phase 4 Update

Irrigation has wrapped up around the building & newly installed landscaping and back filled curbs are now visible. Progress continues in Phase 4 classrooms, counselor’s area, nurses station, & teachers work room.

12/18/2025
Como Success Academy: Phase 4 Classrooms

The newly designed classrooms being renovated on the first and second floors are taking shape with walls going up. Additional Phase 4 progress includes under slab plumbing in the new staff lounge and new storefront doors at the old entrance.

11/26/2025
Como Success Academy: Phase 4 Renovations Progressing

Phase 4 renovation work is moving forward with reconstruction underway. The remaining Phase 3 classrooms and the Media Center have been completed and turned over for district use. The new front entrance has also opened, marking another key milestone for the campus.

10/30/2025
Como Success Academy: Front Entry Completion

Marking another milestone, the new entrance is nearing completion.  Phase 4 demo is currently underway, paving the way for the next stage of improvements.

09/30/2025
Como Success Academy: Phases 2 and 3 Turnover

Phase 2 administrative areas and classrooms, along with Phase 3 classrooms, have been turned over for district use. Additional storage rooms and the new front entry will open in the coming weeks as Phase 4 renovations move forward.

08/22/2025
Como Success Academy: Phases 2 and 3 Scheduled for September Completion

Renovations in Phases 2 and 3 are on track for September completion. Furniture delivery and set up will follow. The newly opened Phase 2 parking lot now provides ample campus parking.

07/29/2025
Como Success Academy: Summer Renovations Nearing Completion

Phase 2 and 3 renovations will continue through the end of summer. Furniture installation and room setup are scheduled for early August. The second portion of the parking lot is being poured and will be ready for the first day of school.

06/26/2025
Como Success Academy: Phase 2 and 3 Renovation Work Continues

Phase 2 renovations continue in the administrative area, with the first round of FFE (Furniture, Fixtures, and Equipment) deliveries expected this July. Gym reconstruction and parking lot work are progressing. Phase 3 demo prep and civil work is underway.

05/27/2025
Como Success Academy: Phase 2 Construction and Site Work Continue

Phase 2 renovation remains underway, including ongoing gym reconstruction and work on the Phase 2 parking lot. Preparations for Phase 3 demolition are scheduled to begin this summer.