Daggett Montessori

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New addition.
  • Minor exterior site improvements.
  • Roofing and structural damage repairs.
  • Renovations and life cycle improvements – MEP, technology and security.
Design Process
Construction Process
801 West Jessamine Street, Fort Worth, TX 76110, USA
Budget
$19,132,903
New Construction
2,510 SF
Renovations
28,020 SF
Trustee
Roxanne Martinez
Construction Starts
May 29, 2025
Anticipated Opening
Continued Use
Anticipated Construction End
Q1 2027

Project Team

Headshot of Garret North.
Garrett North
Owner’s Representative
Headshot of Drew Schott.
Drew Schott
Construction Manager
Contractor
Phillips/May
DLR Group logo.
Architect
DLR Group

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
11/26/2025
Daggett Montessori: Campus Upgrades Continue

Upgrades across campus continue this month, including progress on the gym roof and ongoing restroom improvements in the elementary building. Preparations are also underway for transitioning out of the current administration building with work planned during winter break.

10/30/2025
Daggett Montessori: Building 5 Roofing

Roofing is ongoing at Building 5, New RTUs are installed, and temporary thermostats are in place.  Progress continues, plumbing upgrades are underway in Building 1, while security and network cabling upgrades are wrapping up in Buildings 3, 4, and 5.  Geotechnical field work has been completed and structural repair recommendations are pending.

09/30/2025
Daggett Montessori: Interior Renovations Progressing

Interior upgrades are advancing across campus as fall begins. Building 1 is receiving new plumbing fixtures in restrooms, while Buildings 3, 4, and 5 have started installing upgraded security and communication systems.

08/22/2025
Daggett Montessori: Summer Renovations Complete

Renovations wrapped up on schedule, including MEP upgrades and new HVAC system in Building 5. Site improvements across the campus were also completed, ready to welcome students back for the new school year.

07/29/2025
Daggett Montessori: Interior and Exterior Summer Renovations Near Completion

Interior upgrades in middle school and cafeteria/library spaces are wrapping up. HVAC installation in Building 5 and miscellaneous site improvements are progressing ahead of the start of school.