McLean Consolidation

This Project is Under Construction.

Key Information

Scope of Work:
This project provides a newly constructed facility.

Program Initiatives Addressed:

  • Campus Replacement
  • Campus Consolidation
Design Process
Construction Process
3816 Stadium Drive, Fort Worth, TX 76109, USA
Budget
$73,700,259
New Construction
104,521 SF
Renovations
19,125 SF
Construction Start
September 15, 2026
Anticipated Opening
August 2028
Construction End
Q4 2028

Project Team

Mackenzie Dupons
Owner’s Representative
Pete Valdez
Deputy Program Director
Contractor
JS Waltz + PDQ (JV)
Glenn Partners logo.
Architect
Glenn Partners

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
10/21/2026
McLean Middle School:
Site Cleared for Construction

Demolition of the exterior portables, outside gym, band hall, and science classrooms is complete. This progress has cleared the way for new construction. The first phase of earthwork is set to begin.

09/29/2026
McLean Middle School:
Under Construction

The McLean Middle School Consolidation project has begun construction and Waltz | PDQ (JV) has begun implementing site preparation plans including the installation of construction barricade fencing and tree protection fencing to enclose critical root zones. Fence and wind screens are in place around the construction site perimeter.