Rosemont Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
 
Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
1501 W Seminary Dr, Fort Worth, TX 76115, USA
Budget
$69,833,185
New Construction
25,135 SF
Renovations
177,293 SF
Construction Start
February 17, 2025
Anticipated Opening
July 2027
Anticipated Construction End
Q3 2027

Project Team

Stoney Crump
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Reeder + Summit
Huckabee logo.
Architect
Huckabee

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
06/17/2026
Rosemont Middle School:
Phase 4 & Building Addition

Summer work begins with Phase 4. Demolition is complete in the science labs and west wing classrooms. Underground utility work is underway at the new addition’s site.

05/28/2026
Rosemont Middle School:
Phase 3 Furniture and Fixtures Move In

Phase 3 furniture, fixtures and equipment have arrived and are staged for move in and installation. Phase 4 preparation for renovations have begun with move out and demolition activities.

04/30/2026
Rosemont Middle School:
Phase 3 Wrapping Up

As Phase 3 renovations advance steadily in the women’s locker room, the 1st floor corridors and classrooms begin finishing activities. Upon phase completion, furniture installation and move in will follow.

03/26/2026
Rosemont Middle School:
Phase 3 Progress

Phase 3 renovations are underway, including updates to the women’s locker room. Work in the 1st floor corridors and classrooms is nearing completion, with insulation and drywall wrapping up.

02/25/2026
Rosemont Middle School:
Phase 3 Drywall Era

Phase 3 framing and in-wall rough-in are complete, allowing for drywall installation next.

01/27/2026
Rosemont Middle School:
Phase 3 Update

Phase 3 1st floor classroom demolition is complete. Renovations continue with framing and overhead HVAC equipment installation in progress.

12/17/2025
Rosemont Middle School:
Phase 3, Area E

Phase 3, Area E, 1st floor classroom renovations have begun and are scheduled to be complete by next summer. Site underground utilities relocation has begun and further revisions to the scope of work are planned.

11/26/2025
Rosemont Middle School:
Phase 2 Classrooms Turned Over

Phase 2 classroom renovations on the second floor of the West Campus are now complete and turned over for use. Renovations for the next phase have begun on the first floor, while planning continues for the upcoming administrative addition.

10/31/2025
Rosemont Middle School:
West Campus, 2nd Floor Progress

Classroom improvements and floor renovations on the second floor, Area E, of the West Campus are underway and tracking on schedule to be complete in December.

09/30/2025
Rosemont Middle School:
Phase 2 Renovations Underway

Phase 2 classroom renovations on the second floor of the West Campus are in progress and scheduled for completion in December.