Rosemont Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New building addition connecting the middle school and elementary school to form one campus.
  • Removal of portables and minor site work.
  • Secured front entry and life cycle upgrades
  • Interior renovations – classrooms, labs, media center, commons, and corridors.
Design Process
Construction Process
1501 W Seminary Dr, Fort Worth, TX 76115, USA
Budget
$69,833,185
New Construction
25,135 SF
Renovations
177,293 SF
Trustee
Anael Luebanos
Construction Starts
February 17, 2025
Anticipated Opening
July 2027
Anticipated Construction End
Q3 2027

Project Team

Stoney Crump
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Reeder + Summit
Huckabee logo.
Architect
Huckabee

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
01/27/2026
Rosemont Middle School: Phase 3 Update

Phase 3 1st floor classroom demolition is complete. Renovations continue with framing and overhead HVAC equipment installation in progress.

12/17/2025
Rosemont Middle School: Phase 3, Area E

Phase 3, Area E, 1st floor classroom renovations have begun and are scheduled to be complete by next summer. Site underground utilities relocation has begun and further revisions to the scope of work are planned.

11/26/2025
Rosemont Middle School : Phase 2 Classrooms Turned Over

Phase 2 classroom renovations on the second floor of the West Campus are now complete and turned over for use. Renovations for the next phase have begun on the first floor, while planning continues for the upcoming administrative addition.

10/31/2025
Rosemont Middle School: West Campus, 2nd Floor Progress

Classroom improvements and floor renovations on the second floor, Area E, of the West Campus are underway and tracking on schedule to be complete in December.

09/30/2025
Rosemont Middle School: Phase 2 Renovations Underway

Phase 2 classroom renovations on the second floor of the West Campus are in progress and scheduled for completion in December.

 

08/26/2025
Rosemont Middle School: Renovations Continue

Phase 1 classrooms renovations are completed for the start of school in August. Phase 2 classroom renovations are underway and scheduled for completion in December.

07/31/2025
Rosemont Middle School: Phase 1 and 2 Classroom Renovations Underway

Classroom renovations in Area F are on track for early August occupancy. Additional second-floor work is in progress and scheduled for completion in November. Sewer line replacement began in June as part of site utility upgrades.

06/26/2025
Rosemont Middle School: Phase 1 Renovations Progress, Phase 2 Underway

Renovations in Phase 1 are well underway following May demolition, with progress visible in the second-floor classrooms. Phase 2 began in May, and CFA work kicked off in June.

05/27/2025
Rosemont Middle School: Classroom Renovations Underway

Interior renovations to second-floor classrooms in Area F on the west campus are scheduled for completion in August 2025. The next phase, which includes updates to additional classrooms in Area E, will begin this summer and is expected to be completed by November.

05/27/2025
Rosemont Middle School: Groundbreaking

FWISD, PROCEDEO, Reeder Construction, and Summit officially broke ground on a new connecting building at Rosemont Middle School. The project will unify the middle and elementary schools into one campus and include a new cafeteria, kitchen, and administration area.