Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Construction is progressing on the Phase 4 addition and the Phase 1A storm shelter. Foundation work is underway and crews continue to advance site preparations as the project moves into its next stages.
Progress continues with Phases 1A & 4, which include the new cafeteria, gym, and storm shelter. Courtyard work continues as punch list items from previous phases are wrapping up.
Phases 1B, 2, and 3 are complete with punch list work wrapping up from the summer renovations. Construction is progressing on Phases 1A and 4 as site work continues.
Phases 1B and 3 were completed and turned over for the start of school. Phase 2 is scheduled to wrap up soon, while construction on Phases 1A and 4 begins in September and continues to 2026.
Renovation work in Phases 1, 2, and 3 continues with a focus on completion of all 33 classrooms under construction over the summer. The south parking is anticipated to be ready for the first day of school.
Renovation work in Phases 1 and 2 continues with a focus on two-siding walls and interior finishes. Phase 3 demolition is wrapping up. Civil improvements in the courtyard and teacher parking on the south end remain on schedule for end-of-summer completion.
Construction is ongoing for Phases 1 and 2. Demolition for Phase 3 is scheduled to begin at the start of summer, with civil work continuing throughout the school.
FWISD, PROCEDEO, and Waltz broke ground on a project featuring new additions for cafeteria and fine arts, interior renovations for spaces like the media center, CTE labs, and a storm shelter.
At Meacham Middle School, construction is active across multiple areas with insulation, ductwork, and grading in progress. Electrical preparation continues, and new exterior door demolition has begun in Phase 2.
W.A. Meacham Middle School is currently under construction starting with the renovation and storm shelter addition of the north side of the school. Pictured you can see the aerial photo of the east side of the school showing the ongoing civil work that needs to complete for the new cafeteria and competition gym addition starting in the summer.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.
