Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Key Improvements:
Underground installation work is underway with slab supports, rebar placement, and MEP sleeves. The concrete pour is planned for the end of month. In Phase 1A Storm Shelter addition, work is beginning by marking locations and preparing to set the louvers at the ring beam level.
Phase 4 pier drilling currently in progress and the courtyard MEP underground work, including irrigation and drains, is nearing completion. Retaining walls are currently being backfilled and pouring of the slab will follow for the storm shelter.
Construction is progressing on the Phase 4 addition and the Phase 1A storm shelter. Foundation work is underway and crews continue to advance site preparations as the project moves into its next stages.
Progress continues with Phases 1A & 4, which include the new cafeteria, gym, and storm shelter. Courtyard work continues as punch list items from previous phases are wrapping up.
Phases 1B, 2, and 3 are complete with punch list work wrapping up from the summer renovations. Construction is progressing on Phases 1A and 4 as site work continues.
Phases 1B and 3 were completed and turned over for the start of school. Phase 2 is scheduled to wrap up soon, while construction on Phases 1A and 4 begins in September and continues to 2026.
Renovation work in Phases 1, 2, and 3 continues with a focus on completion of all 33 classrooms under construction over the summer. The south parking is anticipated to be ready for the first day of school.
Renovation work in Phases 1 and 2 continues with a focus on two-siding walls and interior finishes. Phase 3 demolition is wrapping up. Civil improvements in the courtyard and teacher parking on the south end remain on schedule for end-of-summer completion.
Construction is ongoing for Phases 1 and 2. Demolition for Phase 3 is scheduled to begin at the start of summer, with civil work continuing throughout the school.
FWISD, PROCEDEO, and Waltz broke ground on a project featuring new additions for cafeteria and fine arts, interior renovations for spaces like the media center, CTE labs, and a storm shelter.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.
