Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
Structural steel erection is nearing completion in the Kitchen/Cafeteria Addition, to be followed by decking. Framing is complete at the Fine Arts Addition, drywall is staged for installation. Masonry vaneer installation at the Courtyard is in progress.
Renovations in the existing admin wing remain actively under construction, with wall finishes and room build-outs nearing completion. The Fine Arts Addition continues to rapidly advance.
Work is underway across multiple areas, including locker room renovations and interior improvements in the Athletic Wing. Structural work is progressing in the Cafeteria/Gym Addition. The Fine Arts Addition continues advancing toward upcoming inspections.Â
Slab supports, rebar placement, and MEP sleeve installation were completed, enabling the concrete slab pour for the new Kitchen/Cafeteria foundation.
Underground installation work is underway with slab supports, rebar placement, and MEP sleeves. The concrete pour is planned for the end of month. In Phase 1A Storm Shelter addition, work is beginning by marking locations and preparing to set the louvers at the ring beam level.
Phase 4 pier drilling currently in progress and the courtyard MEP underground work, including irrigation and drains, is nearing completion. Retaining walls are currently being backfilled and pouring of the slab will follow for the storm shelter.
Construction is progressing on the Phase 4 addition and the Phase 1A storm shelter. Foundation work is underway and crews continue to advance site preparations as the project moves into its next stages.
Progress continues with Phases 1A & 4, which include the new cafeteria, gym, and storm shelter. Courtyard work continues as punch list items from previous phases are wrapping up.
Phases 1B, 2, and 3 are complete with punch list work wrapping up from the summer renovations. Construction is progressing on Phases 1A and 4 as site work continues.
Phases 1B and 3 were completed and turned over for the start of school. Phase 2 is scheduled to wrap up soon, while construction on Phases 1A and 4 begins in September and continues to 2026.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.
