W.C. Stripling Middle School

Under Construction

Key Information

Project includes the construction of a new three-story building addition along with major renovations to the existing facility. Exterior envelope improvements include existing window and roof replacement. New parking areas are also planned.

Design Process
Construction Process
2100 Clover Place, Fort Worth, TX 76107, USA
Budget
$60,426,944
New Construction
58,400 SF
Renovations
75,200 SF
Construction Starts
April 2, 2024
Anticipated Opening
September 28, 2026
Trustee
Kevin Lynch

Project Team

Nate Moser
Owner’s Representative
Headshot of Edsel Gaitonde.
Edsel Gaitonde
Construction Manager
Contractor
SEDALCO / Post L
Architect
Hahnfield Hoffer Stanford

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/22/2024
W.C. Stripling MS: Making Foundational Progress

Sedalco & Post L continue to make progress on the steel beams, decking & interior wall framing for Stripling Middle School’s new Addition Building. The foundation wall for the Addition is nearly complete. The team has also began the stone restoration process for the existing building’s exterior.

06/20/2024
W.C. Stripling MS: Building the Foundation

Summer renovation for Stripling Middle School is underway. This month, Sedalco & Post L have completed asbestos and started the demolition process. The crew is now working on forming the concrete for the foundation walls. The concrete contractor is also working on the parking lot expansions located on the North and West sides of the campus. Parking expansions should be ready for use this Fall of 2024.

05/20/2024
W.C. Stripling MS: Under Construction!

As of April 2, 2024, W.C. Stripling Middle School is officially under construction! The team is nearly finished with pier drilling, and has started the foundation wall framing, underground electrical and drainage work. The water line associated with the Addition building will also need to be relocated and replaced.

The development site for Stripling MS requires a temporary electrical shut down for about a month, scheduled to begin near the end of May.

 

 

10/18/2023
W.C. Stripling MS: Interior Conceptual Renderings

Interior conceptual renderings of W.C. Stripling Middle School; Reflecting a renovated historical entry, and a window lit view of the 2nd and 3rd floor opening in the prospective new building addition.