Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
Program Initiatives Addressed:
Track restoration marks the project’s final remaining milestone. Lane striping is currently underway and turnover is anticipated this month.
All new and renovated indoor spaces are complete and in use. Outdoor improvements are nearing completion, including landscaping, irrigation, and track surfacing. Final punch-list items and closeout activities are wrapping up, with completion anticipated in early fall.
The campus’s outdoor enhancements represent the final phase of the project. All new and renovated spaces are complete and in use. Remaining efforts continue to focus on the final punch list, with outstanding items being addressed and completed.
Exterior improvements continue to progress, including track replacement and upcoming courtyard revitalization. Work remains focused on completing these final site enhancements and beginning closeout activities.
Finishing and punchlist items are wrapping up. Preparation for completion and closeout activities will soon follow.
Renovations in the northwest corner have made steady progress. Flooring, ceiling and finishing activities are nearing completion. Moisture conditioning has been completed at the school track.
Phase 5 progress continues with overhead MEP work throughout. Wall tile and ceiling grid installation expands across all three floors as rough-ins finish out.
Renovations in the northwest corner are progressing across all three floors, including interior finishes and framing. Auditorium scaffolding is in place for fire suppression upgrades. The project remains on track for late summer completion.Â
The newly renovated and ADA compliant gym balcony has just been turned over to the school for their use. The new bus drop off lane has also been completed and the renovations to the North half of the building continue on schedule.
Students and staff have moved into and began using the newly renovated classrooms on the Southern half of the existing school. The new bus drop off lane is under construction and the last phase of renovations have begun.
PROCEDEO is the Owner’s Representative for the 2021 FWISD Bond that was approved by Fort Worth voters in November of 2021.