W.C. Stripling Middle School

This Project is Under Construction

Key Information

Project includes the construction of a new three-story building addition along with major renovations to the existing facility. Exterior envelope improvements include existing window and roof replacement. New parking areas are also planned.

Design Process
Construction Process
2100 Clover Lane, Fort Worth, TX 76107, USA
Budget
$60,426,944
New Construction
58,500 SF
Renovations
91,400 SF
Construction Starts
April 2, 2024
Anticipated Opening
September 28, 2026
Trustee
Kevin Lynch

Project Team

Nate Moser
Owner’s Representative
Headshot of Edsel Gaitonde.
Edsel Gaitonde
Construction Manager
Contractor
SEDALCO / Post L
Architect
Hahnfield Hoffer Stanford

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
09/23/2024
W.C. Stripling MS: “Topping Out” Ceremony!

On Friday September 20, 2024, Fort Worth Independent School District hosted a “Topping Out” Ceremony to celebrate the structure completion of the new addition building at W.C. Stripling Middle School. The District, community, Sedalco & Post L Group, Hahnfield Hoffer Stanford, alongside Procedeo Group were in attendance. The Stripling MS band and cheer squad also made an appearance.

The last steel beam was intentionally painted white for the community and partners to sign and commemorate this significant milestone as we continue to make construction progress at Stripling Middle School!

 

09/03/2024
W.C. Stripling MS: Renovation Work in Progress!

Sedalco & Post L Group have made headway on the existing W.C. Stripling Middle School campus. Renovation work is nearly complete and consists of, but not limited to, a newly renovated faculty lounge, SPED rise classroom, renovated hallways and a new outdoor basketball court. A new fire pump & sprinkler system is also being installed.

09/03/2024
W.C. Stripling MS: Addition Building in Progress

Tremendous construction progress has been made so far at W.C. Stripling Middle School. Concrete walls at the new storm shelter will be poured during the second week of September 2024. The structure steel for the Addition building is scheduled to be finished mid-September 2024 as well.

08/22/2024
W.C. Stripling MS: We’re Going Vertical!

The new addition building for W.C. Stripling Middle School has gone vertical! During the month of August 2024, our contractors, Sedalco & Post L, have began the installation of the new building’s structural steel foundation, alongside formation of the concrete walls where the storm shelter will be located. Construction for the new addition building is scheduled through Summer of 2025.

07/22/2024
W.C. Stripling MS: Making Foundational Progress

Sedalco & Post L continue to make progress on the steel beams, decking & interior wall framing for Stripling Middle School’s new Addition Building. The foundation wall for the Addition is nearly complete. The team has also began the stone restoration process for the existing building’s exterior.

06/20/2024
W.C. Stripling MS: Building the Foundation

Summer renovation for Stripling Middle School is underway. This month, Sedalco & Post L have completed asbestos and started the demolition process. The crew is now working on forming the concrete for the foundation walls. The concrete contractor is also working on the parking lot expansions located on the North and West sides of the campus. Parking expansions should be ready for use this Fall of 2024.

05/20/2024
W.C. Stripling MS: Under Construction!

As of April 2, 2024, W.C. Stripling Middle School is officially under construction! The team is nearly finished with pier drilling, and has started the foundation wall framing, underground electrical and drainage work. The water line associated with the Addition building will also need to be relocated and replaced.

The development site for Stripling MS requires a temporary electrical shut down for about a month, scheduled to begin near the end of May.

 

 

10/18/2023
W.C. Stripling MS: Interior Conceptual Renderings

Interior conceptual renderings of W.C. Stripling Middle School; Reflecting a renovated historical entry, and a window lit view of the 2nd and 3rd floor opening in the prospective new building addition.