W.C. Stripling Middle School

This Project is Under Construction.

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
2100 Clover Ln, Fort Worth, TX 76107, USA
Budget
$58,426,944
New Construction
58,549 SF
Renovations
91,443 SF
Construction Start
April 2, 2024
Anticipated Opening
Continued Use
Construction End
Q4 2026

Project Team

Mackenzie Dupons
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Sedalco | Post L JV
Architect
Hahnfield Hoffer Stanford

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
10/21/2026
W.C. Stripling Middle School:
Track Nears Completion

Track restoration marks the project’s final remaining milestone. Lane striping is currently underway and turnover is anticipated this month.

09/28/2026
W.C. Stripling Middle School:
Final Stages

All new and renovated indoor spaces are complete and in use. Outdoor improvements are nearing completion, including landscaping, irrigation, and track surfacing. Final punch-list items and closeout activities are wrapping up, with completion anticipated in early fall.

08/28/2026
W.C. Stripling Middle School:
Approaching Completion

The campus’s outdoor enhancements represent the final phase of the project. All new and renovated spaces are complete and in use. Remaining efforts continue to focus on the final punch list, with outstanding items being addressed and completed.

07/30/2026
W.C. Stripling Middle School:
Outdoor Enhancements

Exterior improvements continue to progress, including track replacement and upcoming courtyard revitalization. Work remains focused on completing these final site enhancements and beginning closeout activities.

06/17/2026
W.C. Stripling Middle School:
Wrapping Up

Finishing and punchlist items are wrapping up. Preparation for completion and closeout activities will soon follow.

05/27/2026
W.C. Stripling Middle School:
Phase 5 Completion

Renovations in the northwest corner have made steady progress. Flooring, ceiling and finishing activities are nearing completion. Moisture conditioning has been completed at the school track.

04/22/2026
W.C. Stripling Middle School:
Phase 5 Update

Phase 5 progress continues with overhead MEP work throughout. Wall tile and ceiling grid installation expands across all three floors as rough-ins finish out.

03/25/2026
W.C. Stripling Middle School:
Phase 5

Renovations in the northwest corner are progressing across all three floors, including interior finishes and framing. Auditorium scaffolding is in place for fire suppression upgrades. The project remains on track for late summer completion. 

01/27/2026
W.C. Stripling Middle School:
Updated Gym Balcony

The newly renovated and ADA compliant gym balcony has just been turned over to the school for their use. The new bus drop off lane has also been completed and the renovations to the North half of the building continue on schedule.

12/30/2025
W.C. Stripling Middle School:
New Bus Drop Off Lane

Students and staff have moved into and began using the newly renovated classrooms on the Southern half of the existing school. The new bus drop off lane is under construction and the last phase of renovations have begun.