W.C. Stripling Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.
 
Program Initiatives Addressed:

  • Building Addition(s)
  • Classrooms and Science Labs
  • Media Center
  • Cafeteria/Cafetorium
  • Collaboration Space(s)
  • Interior Corridors
  • Secured Front-Entry Vestibule
  • Security and Life Safety Upgrades
  • MEP (Building Utilities)
  • Accessibility and Site Improvements
  • Furniture, Fixtures and Equipment
  • Technology and Digital Upgrades
  • Removal of Portable Building(s)
Design Process
Construction Process
2100 Clover Ln, Fort Worth, TX 76107, USA
Budget
$60,426,944
New Construction
58,549 SF
Renovations
91,443 SF
Construction Start
April 2, 2024
Anticipated Opening
Continued Use
Anticipated Construction End
Q3 2026

Project Team

Mackenzie Dupons
Owner’s Representative
Pete Valdez
Senior Construction Manager
Contractor
Sedalco | Post L JV
Architect
Hahnfield Hoffer Stanford

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
06/17/2026
W.C. Stripling Middle School:
Wrapping Up

Finishing and punchlist items are wrapping up. Preparation for completion and closeout activities will soon follow.

05/27/2026
W.C. Stripling Middle School:
Phase 5 Completion

Renovations in the northwest corner have made steady progress. Flooring, ceiling and finishing activities are nearing completion. Moisture conditioning has been completed at the school track.

04/22/2026
W.C. Stripling Middle School:
Phase 5 Update

Phase 5 progress continues with overhead MEP work throughout. Wall tile and ceiling grid installation expands across all three floors as rough-ins finish out.

03/25/2026
W.C. Stripling Middle School:
Phase 5

Renovations in the northwest corner are progressing across all three floors, including interior finishes and framing. Auditorium scaffolding is in place for fire suppression upgrades. The project remains on track for late summer completion. 

01/27/2026
W.C. Stripling Middle School:
Updated Gym Balcony

The newly renovated and ADA compliant gym balcony has just been turned over to the school for their use. The new bus drop off lane has also been completed and the renovations to the North half of the building continue on schedule.

12/30/2025
W.C. Stripling Middle School:
New Bus Drop Off Lane

Students and staff have moved into and began using the newly renovated classrooms on the Southern half of the existing school. The new bus drop off lane is under construction and the last phase of renovations have begun.

11/26/2025
W.C. Stripling Middle School:
South Wing Renovations Complete

Renovations on the south side of the campus are now complete, including new classrooms and collaboration spaces. Renovation work on the north side is scheduled to begin following the Thanksgiving break.

10/31/2025
W.C. Stripling Middle School:
Finalizing South Wing Renovations

Renovations are almost complete on the south side of the existing building. Contractors are finishing the final interior details, and the newly renovated area is scheduled for turnover to the school in mid-November. Work on the north side renovations will begin shortly after the south side is complete.

09/30/2025
W.C. Stripling Middle School:
South Wing Renovations Progressing

Renovations on the south side of campus are on schedule for November completion. Wall framing is in place on all floors, with painting and tile work underway. Balcony handrail framing is complete, and new wood flooring installation will begin soon.

08/26/2025
W.C. Stripling Middle School:
Renovated Spaces Open for School Year

The new addition and renovated cafeteria opened on the first day of school. Renovations in the South section of the existing building are moving forward with demolition complete and framing underway.