W.C. Stripling Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • New 3-story building Addition.
  • Major renovations to existing building.
  • Exterior envelope improvements – window/roof replacement.
  • New parking areas.
Design Process
Construction Process
2100 Clover Lane, Fort Worth, TX 76107, USA
Budget
$60,426,944
New Construction
58,549 SF
Renovations
91,443 SF
Construction Starts
April 2, 2024
Anticipated Opening
Q3 2026
Trustee
Kevin Lynch

Project Team

Nate Moser
Owner’s Representative
Headshot of Edsel Gaitonde.
Edsel Gaitonde
Construction Manager
Contractor
SEDALCO / Post L
Architect
Hahnfield Hoffer Stanford

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
08/26/2025
W.C. Stripling Middle School: Renovated Spaces Open for School Year

The new addition and renovated cafeteria opened on the first day of school. Renovations in the South section of the existing building are moving forward with demolition complete and framing underway.

07/29/2025
W.C. Stripling Middle School: Addition Ready for the School Year

Furniture has been delivered and staff are moving into new office spaces. The renovated cafeteria, new flooring, and window installation are nearing completion as final touches wrap up.

06/26/2025
W.C. Stripling Middle School: Addition Nears Completion, Renovation Progressing

Final interior work nears completion. Crews are working through punchlist items and preparing classrooms for furniture delivery in July. Interior renovations to the existing building are progressing in time for the new school year.

05/27/2025
W.C. Stripling Middle School: Final Interior Work Nearing Completion

The new classroom addition is in its final stages, with punch list items scheduled to begin mid-June. Interior renovations in the existing building are underway in preparation for the next school year.

04/30/2025
W.C. Stripling Middle School: Stripling Middle School Moves Forward on Interior Finishes

W.C. Stripling Middle School recently completed exterior brickwork, and HVAC systems are now operational. Inside, flooring, cabinetry, lighting, and other finishes are being installed throughout the new building.

03/31/2025
W.C. Stripling Middle School: Spring Update

Progress continues to be made on exterior brick and glazing. During spring break, electrical power to the new addition was energized. Interior finishes continue to make good progress on all floors.

01/30/2025
W.C. Stripling MS: Ongoing Progress at the Addition Building!

Sedalco & Post L Group continue to make progress on the addition building at Stripling Middle School. Pictured are progress photos of the the new main entrance to the school. Exterior brick work is ongoing for the South elevation area. The installation of interior drywall and interior MEP rough-in, as well as framing inside the new Band Hall is also ongoing.

 

 

11/21/2024
W.C. Stripling MS: An Update on the Addition Building

Pictured are construction progress photos taken in late November 2024 of the new three-story Addition Building. The steel structure is complete (see previous post), and exterior framing is ongoing, but making tremendous progress. Interior electrical, plumbing, and HVAC rough-in is also on-going.

Sedalco & Post L Group, our general contractor for Stripling Middle School, are progressing through Phase 1 & 2 of construction that began in Q2 of 2024. So far, the Southwest area of the existing building is complete! (see previous project update post on 09/03/2024 for details).

09/23/2024
W.C. Stripling MS: “Topping Out” Ceremony!

On Friday September 20, 2024, Fort Worth Independent School District hosted a “Topping Out” Ceremony to celebrate the structure completion of the new addition building at W.C. Stripling Middle School. The District, community, Sedalco & Post L Group, Hahnfield Hoffer Stanford, alongside Procedeo Group were in attendance. The Stripling MS band and cheer squad also made an appearance.

The last steel beam was intentionally painted white for the community and partners to sign and commemorate this significant milestone as we continue to make construction progress at Stripling Middle School!

 

09/03/2024
W.C. Stripling MS: Renovation Work in Progress!

Sedalco & Post L Group have made headway on the existing W.C. Stripling Middle School campus. Renovation work is nearly complete and consists of, but not limited to, a newly renovated faculty lounge, SPED rise classroom, renovated hallways and a new outdoor basketball court. A new fire pump & sprinkler system is also being installed.