Wedgwood Middle School

This Project is Under Construction

Key Information

Scope of Work:
This project includes a combination of new construction, building renovations, and site improvements.

 

Key Improvements:

  • Two new building additions.
  • Renovations to the existing building.
Design Process
Construction Process
3909 Wilkie Way, Fort Worth, TX 76133, USA
Budget
$61,694,266
New Construction
38,436 SF
Renovations
110,787 SF
Construction Starts
July 25, 2024
Anticipated Opening
Q2 2026
Trustee
Anne Darr

Project Team

Nate Moser
Owner’s Representative
Headshot of Edsel Gaitonde.
Edsel Gaitonde
Construction Manager
Contractor
Cadence McShane / Morales
WRA logo.
Architect
WRA Architects

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
07/29/2025
Wedgwood Middle School: Renovations Prepare Campus for Fall

Renovated cafeteria, media center, and new classrooms will be ready for the new school year. The two new additions are progressing towards a fall completion. The 2nd Floor classroom demolition has started.

06/26/2025
Wedgwood Middle School: Interior Renovations and Summer Work Underway

Exterior and interior upgrades continue on track. Crews are wrapping up HVAC installations and window replacements. Ongoing progress inside the new administrative areas.

05/27/2025
Wedgwood Middle School: Framing Progress and Summer Renovations Planned

Structural steel is complete, and both exterior and interior wall framing are underway on the new additions. Interior renovations have also begun. This summer, construction will focus on the kitchen, cafeteria, restroom, and corridor areas.

04/30/2025
Wedgwood Middle School: Classroom Turnovers and Renovations Continue

April brought the successful turnover of 14 classrooms and office spaces at Wedgwood Middle School. Renovation work continues, with active progress on the new entrance and Fine Arts addition.

03/31/2025
Wedgwood Middle School: Spring Update

Structural steel for new main entrance has begun. Steel will soon follow for the new Fine Arts addition. Interior renovations continue working towards the next classroom turnover.

01/30/2025
Wedgwood MS: Classroom Renovation Progress

Pictured are completion photos of newly refreshed and renovated classrooms and hallway at Wedgwood Middle School. Classroom renovations in other areas of the existing school building are ongoing.

Cadence McShane and Morales have also made progress installing the concrete foundation for the new main entrance and foundation building.

12/19/2024
Wedgwood MS: Wrapping up the Year!

Concrete grade beam formwork is in progress at the new Administration addition building and new Fine Arts addition building at Wedgwood Middle School. The contractor, Cadence McShane, has also started interior reservations on the north side of campus- which include a teacher’s planning and workroom area, general classrooms and science classrooms.

 

11/22/2024
Wedgwood MS: November Construction Progress!

The contractor, Cadence McShane, continues the site preparation and renovations on the Wedgwood Middle School project. Pictured are construction progress photos of the new drywall, ceiling, and flooring installations occurring in the existing building, as well as utility work necessary for the new Administration and Fine Arts addition buildings.

09/19/2024
Wedgwood MS: Preparing for Construction!

The Wedgwood Middle School project is officially in construction! The contractor, Cadence McShane, has fully mobilized and is now on site. Interior demolition (as shown) is underway and making significant progress. Site demolition and preparation for the new Administration Addition building will start the last week of September 2024.

06/20/2024
Wedgwood MS: Exterior Conceptual Renderings

Wedgwood Middle School is in the process of completing 100% Construction Documents, obtaining a GMP and all permits necessary to start construction in Q3 of this year. Pictured are conceptual renderings of the proposed main entry and facade.