This Project is Under Construction

Key Information

The Como Success Academy will receive major interior renovations throughout the campus. These include a new secured front entry vestibule, corridor upgrades, media center upgrades for student collaboration. The scope will also include life cycle improvements including mechanical, electrical, and plumbing (MEP), technology, security, interior finishes, and roof upgrades. There will be minor exterior site improvements. The exterior windows will be designed to emulate the original design and a new entrance canopy on Libbey Avenue will provide a welcoming front door to the community.

 

 

Design Process
Construction Process
4001 Littlepage Street, Fort Worth, TX, USA
Budget
$17,637,150
New Construction
N/A
Renovations
54,900 SF
Construction Starts
September 3, 2024
Anticipated Opening
Q1 2026
Trustee
Kevin Lynch

Project Team

Headshot of Cale Wilkinson.
Cale Wilkinson
Owner’s Representative
Headshot of Drew Schott.
Drew Schott
Construction Manager
Contractor
Teinert Construction
Architect
Kline Hardin

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
03/31/2025
Como Success Academy: Spring Update

Como Success Academy has currently completed Phase 1. Teinert Construction has moved into Phase 2 (new Administrative Area), first and second floor abatement has been completed and the renovation has started. In April the Gym will go under construction getting a head start on the summer work that is starting in May. Site work is also ongoing with the new front entrance on the south side of the school. Phase 1 of the new parking lot in use until the completion of the full scale which will be turned over at project completion.

01/30/2025
Workforce Based High School: Abatement and Demolition are Complete!

Construction progress at Workforce Based High School has continued as we enter into Q1 of 2025. First and second floor abatement, demolition, and overhead MEP are completed! Teinert is now focused on interior work- painting and wall tile installation.

Some site work is also complete- specifically the rough-grading at the parking lot. Utility work is ongoing through February 2025.

11/22/2024
Workforce Based High School: Site Preparation & Renovations are Underway!

The Workforce Based High School project began construction in Q3 of 2024. Since September, the contractor, Teinert, has completed abatement and demolition in necessary areas and is now focused on framing and MEP installations throughout the campus. Utility work on site grounds is also in progress.

05/21/2024
Workforce Based HS: Progressing through Design Phase

The Workforce Based High School program is currently progressing through the construction document phase of design. Teinert is tentatively scheduled to start renovations in Q3 of 2024.

02/23/2024
Workforce Based HS: Conceptual Media Center

Interior conceptual renderings of the new media center at Workforce Based High School Program.

10/19/2023
Workforce Based HS: Exterior Conceptual Renderings

Exterior conceptual renderings of the Workforce Based High School Program; Reflecting a renovated front entry and parking area.

10/19/2023
Workforce Based HS: Interior Conceptual Renderings

Interior conceptual renderings of the Workforce Based High School Program; Reflecting a renovated front vestibule, hallway and entry.